Overview
No construction firm or supplier wants to go to trial. But if it comes to that, you want to be sure to have experienced counsel in your corner. Our Construction & Public Contracts lawyers are trial lawyers. Respected by judges, hearing officers, arbitrators, and opposing counsel for our skill and tenacity, we deliver excellent results for our clients.
A battle-tested force equal to any adversary.
We are highly regarded by our peers for our ability to resolve a majority of disputes through robust negotiation and cost-effective, time-saving methods such as Alternative Dispute Resolution (ADR). Should litigation prove necessary, our Construction & Public Contracts team is prepared to challenge even the most formidable and well-funded opposition.
Services
We help clients resolve complex disputes—with and without litigation. Our services include:
Project-Related Disputes
- Bid protests
- Scope disputes
- Differing site conditions
- Construction defects
- Delay, disruption, and interference
- Acceleration
Financial Disputes
- Liens
- Surety bonds
- Proprietary specifications
- Liquidated damages
- Cost accounting
- Insurance coverage
- Builder’s risk insurance
- Indemnification agreements
Employment Disputes
- Lost productivity
- Termination
Materials Disputes
- Design errors and omissions
- Safety failures
- Warranties
- Hazardous materials and other environmental issues
Experience
Breaking New Ground in Construction Litigation
After almost 300 days of arbitration and numerous trial court appeals, Hinckley Allen settled one of the last contractor disputes related to Boston’s “Big Dig” for $88.7 million. The total recovery on a single contract was $183 million in favor of a joint venture of Tutor Perini, Kiewit Corp. and Jay Cashman. The litigation took place over 15 years, involving more than 30 Superior Court actions and four appeals.
$5.3 Million Arbitration Award for Connecticut Developer
We helped secure a $5.3 million arbitration award against an architect for damages due to design errors and omissions after 12 days of hearings for our client, Stonington Water Street Associates, the developer of a Connecticut condominium complex. As reported in the legal press, this is believed to be the largest arbitration award ever against an architect in the state of Connecticut.
Claim, Counterclaim for Damages In Excess of $4Mfor PPL SavageALERT
We were retained by PPL SavageALERT, Inc. to pursue a breach of contract claim against ASML US, Inc. for non-payment under a design/build contract for a natural gas combined heat and power system. After PPL initiated arbitration before the AAA, ASML counterclaimed for breach of contract, breach of warranty and rescission, and sought damages in excess of $4M.
ASML’s counterclaims were premised on the contentions that the system failed to perform at an allegedly agreed-upon availability factor of 95% and that it experienced unanticipated transformer and bearing malfunctions due to manufacturing defects. During a week-long arbitration, Hinckley Allen focused on establishing for the arbitrator that no such availability warranty had been made and that the malfunctions experienced by ASML were caused by its own negligence and circumstances beyond PPL’s control. Following the completion of the arbitration, the arbitrator rendered a well-reasoned decision dismissing ASML’s counterclaims in total and awarding PPL its entire contract balance, plus interest.
Case Studies
Hinckley Allen Secures Landmark Summary Judgment Decision for a Construction Client in $100M+ Litigation Battle
In September 2023, Hinckley Allen achieved a monumental victory in securing summary judgment on behalf of a national privately-held construction client (“Contractor”). This triumph was secured on a complex infrastructure project (“Project”) in Miam…
Hinckley Allen Secures $30m Settlement for NY Wastewater Treatment Plant
Retained by the City of Binghamton, NY, the Village of Johnson City, NY, and the parties’ Joint Sewage Treatment Board, Hinckley Allen settled a complex lawsuit stemming from the dramatic collapse of part of the Binghamton-Johnson City Joint Sewage Treat…
Newsroom
Video: Protecting Your Secrets – Understanding the Power of Attorney-Client Privilege
September 28, 2023Attorney-client privilege is designed to protect the communication between lawyer and client. For something to fall within the scope of attorney-client privilege, it must be both confidential and designed to give legal advice. Simply adding an attorney to …
Impossibility of Performance, Frustration of Purpose, and Force Majeure: What Happened to These COVID Catchphrases?
July 30, 2023This article was featured in the Vol. 114, July 2023 edition of the Construction Industries of Massachusetts, Inc.'s Construction Journal.Believe it or not, it has been more than 3 years since the Commonwealth of Massachusetts declared a state of emergency…
Hinckley Allen Construction Practice Named to The Top 50 Construction Law Firms™ for 2022
June 1, 2022Hinckley Allen is proud to announce that it was ranked 13th in The Top 50 Construction Law Firms™ by Construction Executive magazine.Associated Builders and Contractors Service Corporation, a national industry trade organization consisting of 21,000 memb…
Hinckley Allen Construction Practice Named to The Top 50 Construction Law Firms™
June 7, 2021Hinckley Allen is proud to announce that it was ranked 12th in The Top 50 Construction Law Firms™ by Construction Executive magazine.Associated Builders and Contractors Service Corporation, a national industry trade organization consisting of 21,000 memb…